6/22/17- Posted below is the most recent construction update. 

________________________________________________________________________

Construction Update
Roxbury Northfield (VT 12A)
ER STP 0187(13)

                                                                      

Project Location: The project extends along VT 12A from about ¾ of a mile north of the Granville/Roxbury Town Line in Roxbury to the Northfield Village Limits for a distance of 9.6 miles.

Saturday, June 24, 2017 – Crews are scheduled to complete paving of the second of four layers of new pavement Saturday, weather permitting.

Week of June 26, 2017

Northfield –

  • A culvert north of Lover’s Lane is scheduled to be replaced this week. Estimated timing to complete the work is approximately 2 days.
  • Milling on VT 12A north of Roxbury Village is expected to start during the week of July 3rd, after the July 4th holiday.  

Roxbury –

  • Driveway entrances will be prepared for paving of driveway aprons.
  • Crews will be cleaning out ditch lines between Sullivan Hill Road and the south end of the project.

Travel will be reduced to one lane with alternating one way traffic around all operations.  Flaggers will be present to assist in maintaining traffic flow.

Traffic – Traffic delays are expected this week.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone.

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994. Construction updates will be posted at www.roadworkupdates.com