8/17/17 Posted below is the most recent construction update for the project.   

_____________________________________________________________________________

Construction Update
Charlotte US 7 Reconstruction
FEGC 019-4(20)

 Project Location:  US 7 from the Ferrisburgh/Charlotte Town line north for three miles to the Ferry Road Intersection.  Project completion is scheduled for 2018.


Week of August 21st, 2017

 
Wildwood West Development to Ferry Road

Crews will continue installing underdrain and fine grading to prepare for paving.

US 7 traffic is currently using the offline two-way traffic detour along this section of the project.  

East Thompsons Point Road to Wildwood West Development –

Excavation of the trail approach on west side of the newly installed pedestrian underpass near the Lower Old Town Trail will occur this week.  

Traffic will remain using the current pattern on US 7 until the newly constructed 8’ shoulder is paved. 

Traffic:  Two-way traffic will be maintained as much as possible.  Alternating one-way traffic will be utilized while crews prepare and transition the traffic onto the traffic detours.  Flaggers will be present to maintain traffic flow.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone.

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or to view recent updates, visit www.roadworkupdates.com.